Behind the Scenes of a 24-Hour Reagent Delivery
- toddwhanna
- Oct 8
- 1 min read
Our client made a last-minute change to their injection approach last week on a Southern California project under tight regulatory timelines.

They chose a Tersus Environmental suite of reagents, and the Tersus Team sprang into action. Three different reagents (45,500 pounds total) were ordered, shipped, and onsite, ready for injection, all within ~24 hours.
Here’s how it happened:

Wed, Oct 1, 2025 – 5:28 PM: Verbal green light given to Tersus
Thu, Oct 2, 2025 – 8:10 AM: Formal quote issued by Tersus
Thu, Oct 2, 2025 – 8:44 AM: Signed quote returned
Thu, Oct 2, 2025 – 10:42 AM: Next Day Shipments Scheduled

Fri, Oct 3, 2025 – 9:53 AM: Shipment #1 arrives onsite
Fri, Oct 3, 2025 – 12:07 PM: Shipment #2 arrives onsite
Fri, Oct 3, 2025 – 1:24 PM: All reagents offloaded and staged onsite
Fri, Oct 3, 2025 – 1:48 PM: Reagent mixing & injection begins
From the order being placed to injection starting the next day, an incredible display of responsiveness, coordination, and teamwork. Huge shoutout to the entire Tersus Team for making this lightning-fast turnaround possible!